Defining Critical: Slack Less Than or Equal To critical Jan 06, 2021

By default, tasks are critical if Total Slack is less than or equal to 0 days as shown for Tasks 6-8 in the following illustration:

If, however, you need to redefine the number of days that slack is less than or equal to for a task to be flagged as critical, you can do so through the option ...

Continue Reading...
Multiple Critical Paths critical Dec 28, 2020

The critical path, as defined by academia, is known as the longest and the shortest, i.e. the longest path through the network but the shortest amount of time in which the project can be completed as shown for Tasks 6-8 in the following illustration:

If, however, there is a need to review the...

Continue Reading...
Critical Items in Microsoft Project critical Dec 21, 2020

By default, Microsoft Project flags tasks as critical if Total Slack is less than or equal to 0 days. And Microsoft Project calculates critical to the project finish date (10/16) as shown in the following illustration:

But what if the current estimated finish date of the project, which Microsoft...